Project Description:
This project would provide for the reconstruction of 170th Street from Meredith Drive to Waterford Road as well as approximately 1/4 mile of Meredith Drive, east of 170th Street. Both roads will be reconstructed as a four-lane roadway with left-turn lanes, including grading and storm sewer. 170th Street will include the City’s Complete Street policy, with a 5’ sidewalk and 10’ separate bike lane along the west side of the road. Meredith Drive will include a 10’ trail along the north side of the road. This project has received a State Transportation Block Grant to assist with funding.
The Contractor for this project is C.J. Moyna & Sons, LLC, and Progressive Structures, LLC, joint venture. This project is a two-year project and is anticipated to be completed in the Fall of 2023.
Access and Work Zones:
This project will be completed in stages. Please follow posted signs and detours for routing around construction. Please check back here for updates on closures as work progresses.
Maps will be posted to this webpage with additional information. The schedule is subject to change based on weather, conditions in the field, and contractor coordination. Check back to this page for project updates. As always, please use caution in the construction zone and obey all traffic control, for your safety and the safety of others. We appreciate your patience, thank you for your cooperation.
Project Status Update, 06/09/2022:
The Contractor has installed temporary fencing in the corridor. Utility companies are continuing to work on relocations. Grading work will begin in Stage 1, and water main work in Stage 3 as weather permits and as construction materials become available.
Stage 1A will close on Wednesday, June 15; this will be the Meredith Drive reconstruction from east of 170th Street to 167th Street. During this stage, 169th Street intersection will be closed, and the 167th Street and 170th Street intersections will remain open. Water main work will also begin in Stage 3 on Monday, June 13, and will require lane closures when work is done adjacent to the roadway.
Please see the map below for the locations of the stages; this map will be updated when dates are set for closures. Message boards will be posted on the roadway prior to closures to alert residents of upcoming changes. An official detour route will be established, and the Police and Fire Departments will be notified of the closed areas.
Project Maps:
Original source can be found here.